PLEEASE ANWER QUICK: The project manager is writing the requirements document. Which phase of the project life cycle is he in?
project closure
project planning
project initiation
project execution ​

Respuesta :

Animmango
Animmango Animmango
  • 01-05-2021

Answer:

I think, project execution. He is writing the requirements document. which mean it doesn't project closure and initiation. then he did it which mean it doesn't project planning.

Answer Link

Otras preguntas

4) A scuba diver swam 112 feet beneath the surface of the ocean. He then climbs up 63 feet. What is his depth now?
Help i dont understand this please help :(
The temperature is _____ °C
Simplify: 7x + 5 - 4x - 16
A _____ is a group of two or more devices/computers connected together to allow for the exchange and information and for the sharing of resources such as printe
A(n) __________ state is comprised of a single, solitary state without consenting member governments. A. devolved B. unitary C. executive D. federal Please sele
If an automobile slows from 26 m/s to 18 m/s in a period of 4.0 s, what was the average acceleration? a. %005.7 m/s2 b. 4.0 m/s2 c. 7.0 m/s2 d. %002.0 m/s2
Which is an accurate conclution regarding the system of equations below ? Y=2/3x-1 and Y=3-2/3x
I will mark you brain list plz answer ​
In March 1999, Bertrand Piccard and Brian Jones attempted to become the first people to fly around the world in a hot air balloon. Based on the average sped of