12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

The cost of ordering multiple items is sometimes, always or never proportional
What can be what is the answer to 49 divided by ? = ? But the answer cannot be 7
How do say 6:45 a.m. in how Spanish
What does a journal written by frontier settlers most likely tell you about Manifest Destiny?
What kind of precipitation would occur if the temperature was above freezing
If y=-4 when x=10, determine y when x=5
What is the fraction of 16/48
the _______ is where the geosphere meets the ocean
Which point(s) in the water cycle below best illustrate(s) water changing to a gas, and which term(s) could describe it? Is it.. 1; sublimation & evaporati
How are square roots related to the area of a square ?